Business Samsung Plans to Quintuple V9 NAND Output at Its Xi'an X2 Fab From 10,000 to 50,000 Wafers a Month for AI Data Center SSDs Meta Meta's AI Chief Says Superintelligence Is Arriving — and Lawmakers Are Already Quoting Him to Push a Ban AI Agents AWS Ships Five Open Strands Decider v2 Models on Google's Gemma 4, With a 31B Scoring 82.1 and a 98 Percent Cost Cut on Internal Ticketing AI Agents X Square Robot Says WALL-OSS-1.0 Clears 55.1% of 312 Untrained Robot Tasks, More Than Double the pi0.5 Baseline News Microsoft Details Rocket, the In-House RL System Holding a 3-Trillion-Parameter MAI Base 2 Through Month-Long Runs Business Applied Digital Signs an 18-Year, 150 MW Lease Worth $5.4 Billion, Pushing Contracted Backlog Past $41 Billion Security OpenRouter Drops Together AI, Phala and Novita After Canary Prompts Leaked and Revokes Zero-Data-Retention on 125 Endpoints ChatGPT OpenAI Puts GPT-6.2 Sol in the ChatGPT Chat Tab and Sets GPT-5.6 Sol and Terra to Retire on December 23 Business Samsung Plans to Quintuple V9 NAND Output at Its Xi'an X2 Fab From 10,000 to 50,000 Wafers a Month for AI Data Center SSDs Meta Meta's AI Chief Says Superintelligence Is Arriving — and Lawmakers Are Already Quoting Him to Push a Ban AI Agents AWS Ships Five Open Strands Decider v2 Models on Google's Gemma 4, With a 31B Scoring 82.1 and a 98 Percent Cost Cut on Internal Ticketing AI Agents X Square Robot Says WALL-OSS-1.0 Clears 55.1% of 312 Untrained Robot Tasks, More Than Double the pi0.5 Baseline News Microsoft Details Rocket, the In-House RL System Holding a 3-Trillion-Parameter MAI Base 2 Through Month-Long Runs Business Applied Digital Signs an 18-Year, 150 MW Lease Worth $5.4 Billion, Pushing Contracted Backlog Past $41 Billion Security OpenRouter Drops Together AI, Phala and Novita After Canary Prompts Leaked and Revokes Zero-Data-Retention on 125 Endpoints ChatGPT OpenAI Puts GPT-6.2 Sol in the ChatGPT Chat Tab and Sets GPT-5.6 Sol and Terra to Retire on December 23

Applied Digital Signs an 18-Year, 150 MW Lease Worth $5.4 Billion, Pushing Contracted Backlog Past $41 Billion

Applied Digital Signs an 18-Year, 150 MW Lease Worth $5.4 Billion, Pushing Contracted Backlog Past $41 Billion

Applied Digital signed an 18-year lease for 150 MW of critical IT capacity with an unnamed investment-grade hyperscaler, worth about $5.4 billion in base-term revenue and $12.7 billion if all renewal options run to 33 years. Total contracted base-term revenue now exceeds $41 billion, and the portfolio passes 1.6 GW of contracted IT load against 2.2 GW of grid-connected peak load.

Applied Digital said on Monday that it has signed an 18-year lease with a tier-one investment-grade hyperscaler for 150 megawatts of critical IT capacity, a deal the company values at roughly $5.4 billion in base-term contracted revenue, or about $12.7 billion if every renewal option is exercised across a 33-year term. The tenant was not named. The company said the terms carry higher pricing than its previous leases.

The addition takes Applied Digital's total contracted base-term revenue above $41 billion, or close to $100 billion if all renewals run their course. Its portfolio now exceeds 1.6 gigawatts of contracted critical IT load, backed by 2.2 gigawatts of grid-connected peak load, and about 75 percent of base-term revenue is attributable to investment-grade counterparties. For a company that was a bitcoin miner three years ago, the credit profile of the backlog has become the story rather than its size.

It is the second large lease this year. In June the company signed a 15-year agreement for 210 megawatts at its Delta Forge 2 campus worth about $5.2 billion, according to Reuters, which makes the new contract notable less for its headline value than for its duration and price. Eighteen years locks a customer in for the depreciation life of the building, and the higher rate implies that capacity deliverable in 2028 is being priced against a market that is still tightening.

Financing follows a template the company has used before. Chief financial officer Saidal Mohmand said the build will be funded with first-in equity already on the balance sheet and through the $5 billion programmatic equity partnership with Macquarie Asset Management, followed by project financing secured against the long-term lease. He expects to complete the remaining project finance for Delta Forge 1 and Polaris Forge 3 in the first calendar quarter of 2027, and for Delta Forge 2 in the second quarter.

Capacity delivery is expected to begin in the first half of calendar 2028, subject to development milestones, utility arrangements and regulatory approvals. That timeline is the part of the announcement carrying the most risk, because it depends on grid interconnection in a market where large-load queues have become the binding constraint, and on transformers and turbines whose lead times have stretched well beyond two years. A signed lease converts to revenue only after the electrons arrive.

Investors treated the news as validation of the leasing model, with the stock up more than 13 percent in premarket trading, according to Yahoo Finance. Chief executive Wes Cummins framed the deal as evidence of customer relationships rather than of market timing, saying the portfolio reflects the scale of the infrastructure the company has built.

What the numbers do not show is concentration. An investment-grade tenant is a better credit than a startup, but a backlog of $41 billion held by a handful of hyperscalers is a different risk profile from the same figure spread across dozens of customers, and the improved pricing suggests the company has some leverage to press. The open question for 2027 is whether the equity partnership and project debt can be raised at the rates assumed when the leases were signed, since every quarter that data center financing stays expensive erodes the margin on capacity already promised.

Comments (0)

Log in to join the discussion

Log In

No comments yet