Applied Digital, the Dallas-based operator of AI-focused data center campuses, has asked major tenants including Oracle and Meta for billions of dollars in financial guarantees before finalizing their leases, according to a Bloomberg report published Friday that cites a single source familiar with the matter. The guarantees have been in place since at least last year and are meant to secure electrical power for the sites before contracts are signed.
The logic behind the request is straightforward: connecting a large AI data center to the grid is no longer a routine step. Substations, transmission upgrades and on-site electrical infrastructure can cost enormous sums and take years to permit and build. By asking tenants to guarantee those costs, Applied Digital effectively moves the financial risk of grid construction onto the companies that want the compute capacity.
That arrangement reflects a broader shift across the AI infrastructure build-out. Developers and utilities are increasingly unable, or unwilling, to shoulder the upfront cost of power upgrades alone, so the hyperscale tenants are being asked to underwrite the electrical build-out for the facilities they will occupy. The power bill, once an operating expense, is becoming a capital commitment made before the first GPU is installed.
The practice is not unique to one company. OpenAI has separately agreed to pay the full power bill for its planned Georgia campus, a structure that similarly ties the buyer of AI capacity directly to the cost of energy infrastructure. What the Applied Digital report adds is the idea that even mid-sized developers now have enough leverage, in a market where power is the scarce input, to demand multi-billion-dollar commitments from tenants as large as Oracle and Meta.
The economics explain why. A large AI campus can draw as much electricity as a mid-sized city, and utilities in several markets have warned that new large loads face multi-year waits for grid interconnection. When the compute buyer is racing to deploy capacity, the fastest path is often to pay for the electrical infrastructure itself, and guarantees give the developer cover if the tenant later walks away from a half-built substation.
Because the Bloomberg report rests on a single anonymous source and neither Applied Digital, Oracle nor Meta has publicly confirmed the arrangement in detail, the exact size and structure of the guarantees remain unclear. Even so, the direction of travel is hard to dispute: the cost of electrifying the AI boom is steadily migrating from the balance sheets of data center developers to the ones doing the renting.
For the broader industry, the report is another sign that power, not chips, is becoming the binding constraint in AI expansion. The companies that can pre-finance substations and transmission lines will set the pace of deployment, and everyone else, it appears, will be asked to sign for the wiring first.